NOTICE OF PUBLIC HEARING TOWN OF MARSHALL
WASTEWATER PRELIMINARY ENGINEERING REPORT (PER)
The Town of Marshall will hold a public hearing at 6:30 PM on Tuesday, June 71h, 2022 at the Community Room, 16 S Main Street, Marshall, IN 47859.
The Town’s engineering consultant, Wessler Engineering, will present the recommended project, which will include a new sanitary collection system and lift stations for the Town of Marshall that will send its wastewater north to the existing Turkey Run Wastewater Treatment Plant.
The Project will be funded through a Wastewater State Revolving Fund (WWSRF) Loan.
Copies of the required Preliminary Engineering Report (PER) for this project are available for public viewing starting Saturday, May 28th, 2022 through Sunday, June 12, 2022 at the Community Room.
There will be the opportunity for questions and comments from the public at this meeting. Written comments from the public will be accepted through Sunday, June 12, 2022. Your participation is welcome and encouraged. If you require special assistance at this meeting, please contact the Clerk’s office at (765) 562-2627. Kathy Wirth will be able to assist you.
Written comments regarding this project should be sent to Town of Marshall, PO Box 204, Marshall, IN 47859 prior to Sunday, June 12th, 2022, five days after the public hearing.
Kathy Wirth
Town Clerk